| |
|
Corps History - Part 14
The Corps and the First World War (1914-18)
|
|
The Beginning
It is generally regarded that the assassination of Archduke Franz
Ferdinand (1863-1914) of Austria in Serbia was the catalyst that
precipitated the start of the First World War (1914-18).
|
|
Britain's involvement began on 4 August 1914 when Germany invaded neutral
Belgium, and thereby forced Britain to declare war on the aggressor
because Britain was one of the guarantors of Belgium's neutrality,
an arrangement that had been in existence since the founding of
that state in 1831.
At the outset of the war the British Prime Minister, Herbert Asquith
(1852-1928) appointed as his Secretary of State for War the engineer
officer Field Marshal Lord Kitchener (1850-1916). Kitchener predicted
that the war was likely to be protracted therefore he saw a need
for a large army to sustain it. After obtaining Cabinet approval
he set about expanding the Army to over 70 divisions. The newly
raised units were referred to as the New Army (or Kitchener’s
Armies), and the first of them saw active service in 1915.
Tragically, Kitchener was drowned in 1916 whilst travelling to
Russia aboard HMS Hampshire, which struck a mine near Scapa
Flow.
|
A Kitchener First World War recruiting poster.
Field Marshal Lord Kitchener (1850-1916) was commissioned into the
Royal Engineers in 1871. |
| During the war the Corps expanded considerably.
The reasons for the expansion were twofold:
- The need to provide extra field engineering support for
the newly formed armies
- The taking on of new responsibilities by the Royal Engineers,
such as; tunnelling, forestry, quarrying, chemical warfare (gas),
inland water transport, camouflage, postal and the Army Pigeon
Service.
During the the war new survey techniques were developed, which
included: mapping from aerial photographs, 'sound ranging' and 'flash
spotting'. Members of the Corps also developed new equipment and
weapons such as; the Nissen hut, the Mills bomb, the Stokes mortar
and the Fullerphone.
Members of the Corps also displayed great courage for 17 members
of the Corps were awarded Victoria Crosses.
Throughout the war the British Army and the forces of the Empire
fought on many fronts and were accompanied by their engineers:
- Western Front (Belgium and France) - 1914-18
- Egypt and Palestine - 1914-18
- Mesopotamia (now Iraq) - 1914-22
- East and West Africa - 1914-18
- Gallipoli - 1915-16
- The Balkans - 1915-18
- Italy - 1917-18
- Russia - 1918-20
By its own admission the Corps was ill-prepared for the war, as
were other branches of the army; this state came about as an after
effect of the Esher Committee reforms (1904-05) and were made worse
by the inability of the General Staff to give adequate guidance
as to the type of warfare that the army of the twentieth century
was likely to fight. The General Staff had no experience of Continental
warfare and could only draw on their observations and experiences
of the colonial wars of the past.
|
Strength of Royal Engineers - 1914-18
The war produced an unprecedented expansion of the Corps from about
25,000 men in 1914 to approximately 315,000 in 1918 (78% expansion).
|
| Strength of the Royal Engineers
1914-1918
Date |
Rank |
Regulars,
Special Reserve |
Territorial
Force |
Total
All ranks |
Aug
1914 |
Officers
Other ranks |
1,056
10,394 |
513
13,127 |
25,090 |
Aug
1915 |
Officers
Other ranks |
3,049
82,932 |
1,262
38,924 |
126,165 |
Aug
1916 |
Officers
Other ranks |
6,823
154,361 |
48,000* |
209,000* |
Aug
1917 |
Officers
Other ranks |
8,886
230,500 |
56,282 |
295,668 |
Aug
1918 |
Officers
Other ranks |
11,830
225,540
|
310,000* |
| Transportation |
80,000*
|
Nov
1918 |
All ranks |
229,366
|
314,318±
|
| Transportation |
62,344
22,608‡ |
* Approximate figures. ‡
Colonial corps sent from home.
± approx 15,000 were officers
Source: History of the Corps
of Royal Engineers Vol V (p. 43) |
The percentage changes in the proportions of the 'teeth arms' within
the British Expeditionary Force (BEF) also give an indication to
the extent of the expansion of the Corps of the Royal Engineers
during the First World War (1914-18). At the beginning of the war
the Royal Engineers made up nearly 6% of the British Expeditionary
Force (BEF) but by July 1918 that figure had nearly doubled to just
over 11% - see table below:
Royal Engineers
(George V - 1910-36)
cap badge
worn by First World War Royal Engineers. |
| Percentage changes of arms in the BEF (1914-18)
| |
Sep 1914 |
Sep 1915 |
Sep 1916 |
Sep 1917 |
Mar 1918 |
Jul 1918 |
% |
% |
% |
% |
% |
% |
| Cavalry |
9.28 |
3.88 |
3.02 |
2.77 |
1.65 |
1.65 |
| Infantry |
64.64 |
69.89 |
61.74 |
58.69 |
53.71 |
51.25 |
| RFA/RHA |
18.27 |
14.32 |
15.48 |
13.56 |
16.67 |
18.30 |
| RGA |
1.31 |
2.73 |
4.24 |
6.21 |
7.90 |
8.68 |
| Royal Engineers |
5.91 |
7.96 |
10.89 |
12.28 |
10.11 |
11.24 |
| Tank Corps |
- |
- |
0.04 |
0.50 |
1.05 |
1.20 |
| Royal Flying Corps |
0.59 |
0.44 |
1.16 |
1.90 |
3.24 |
- |
RFA - Royal Field Artillery, RHA - Royal
Horse Artillery RGA - Royal Garrison Artillery
Source: The Oxford Illustrated
History of the British Army (p. 216) |
|
The 1914-1918 Royal Engineers roll records
the names of 19,794 men who were either killed or died on service.
|
Home Front - 1914-18
On the Home Front the Royal Engineers were engaged in a variety
of activities to sustain the war effort such as:
- Works programmes; ranging from the provision of accommodation
to land requisition, from forestry to weapon development.
- Coast and Air Defence operations.
- Transportation activities from mobilization by rail to port
and Inland Water Transport operations.
- Signal, Survey and Postal services.
|
Works Activities
The Royal Engineers' Directorate of Fortifications and Works (DFW)
was responsible for identififying, organising, managing and implementing
a variety of Works programmes to sustain the war effort some of
which are given below:
|
Hutting
- Major BHO Armstrong RE designed a series of schemes for hutted camps to suit different types of the units. The schemes were approved by the Army Council and in late August 1914 were distributed to the Commands for the Chief Engineers to supervise construction.
- A separate Directorate for Barracks were established in late
August 1914 to manage the camp construction and maintenance programmes.
|
Design of Armstrong's Sleeping Hut
- 60ft long x 20ft wide x 10ft high.
- Sleep 30 men.
- A gangway ran down the centre for table and benches.
|
|
|
Hutting programme
1914-1918
Command |
Men housed
Dec 1914 |
Men housed
Aug 1918 |
% increase |
| Aldershot |
60,000 |
100,000 |
40% |
| Eastern |
80,000 |
290,000 |
210% |
| Eastern (Central Force) |
50,000 |
- |
- |
| Ireland |
40,000 |
90,000 |
50% |
| London |
10,000 |
10,000 |
0% |
| Northern |
200,000 |
280,00 |
80% |
| Scottish |
15,000 |
50,000 |
35% |
| Southern |
250,000 |
310,00 |
60% |
| Western |
80,000 |
155,000 |
75% |
| Channel Islands |
15,000 |
15,000 |
0% |
Totals |
800,000 |
1,300,000 |
500% |
Source: History of the Corps
of Royal Engineers Vol V (p. 75)
|
|
Rifle Ranges
Colonel J H Cowan (late RE) identified sites for rifle ranges and
supervised their construction, but due to a shortage of ammunition
they could not be used until after 1915. Miniature ranges were constructed
at all camps. |
Hospitals
Schemes were prepared by Major BHO Armstrong RE for hutted hospitals
of 600 beds with all accessory buildings. These schemes were soon
implemented and by 1917 the hutted hospitals acounted for 320,000
military hospital beds in Great Britain.
Land
- In 1914 the Royal Engineers were the responsible custodians of all land and property held by the War Office.
- Once the war started and the Government embarked a series of
land requisitions to accommodate camps (notably at: Catterick,
Ripon, Wareham, Bovington, Swanage, Lulworth and Longmoor), firing
ranges, training grounds etc.
|
No 13 Stationary Hospital, surgical ward -
an example of Major Armstrong's RE hutted hospitals.
(Photo: IWM Q 29155) |
| The Directorate was also involved in Horse Line and
Road construction programmes, as well as, the building of aerodromes
for the Royal Flying Corps, and the managing of Ordnance Depots and
works contracts. |
Coast and Air Defence
The war brought to Britain the traditional threat of coastal attack,
as well as, the new threat of aerial bombing made possible by the
recent technological advances in aeronautics. The Royal Engineers
were soon engaged in developing defences against these new threats.
Their contribution was the development of observation techniques
using searchlights.
Coast defence
Throughout the war the Royal Engineers continued with their responsibility
of maintaining and expanding the coastal defence installations built
by previous generations of Sappers.
In 1914 the command of coast defence areas was divided between
the Royal Artillery and Royal Engineers. The Royal Engineers officers
commanded:
- Thames and Medway Defences
- Scottish Coast Defences
- South Irish Coast Defences
- Liverpool Coast Defences
- Tyne Coast Defences
New Fortress Companies were formed to provide the manpower to man
the searchlight element of the coastal defences, a legacy of the
defunct Royal Engineers Submarine Mining Service (the Service transferred
to the Royal Navy in 1905). In 1915 many former members of Royal
Engineers Submarine Mine Service were transferred to the newly formed
Royal Marines Submarine Mine Service established to lay and operate
defence minefields in the Channel off Dover.
Air defence
Aerial attack was a new form of warfare introduced through the
advances in airship and aircraft technology. The first bombing raid
on Britain took place in December 1914 when German Zeppelin airships
dropped bombs in the Dover area. Thereafter Zeppelin bombing raids
continued on London, as well as on locations on the East coast and
on one occasion on Chester. In 1916 the Germans switched from using
airships to aeroplane (Gothas).
|
| As a consequence of the air attacks 50th Field Searchlight (FSL)
Company RE was reformed in 1915 to provide searchlight anti-aircraft
(AA) defence for London. The Tyne Electrical Engineers took over
the running of the School of Electric Lighting, Gosport and operated
it until the end of the war. By December 1915 AA searchlights units
were raised as part of the Royal Engineers (TF) and deployed in
the defence of industrial cities and ports throughout Britain.
|
Anti-aircraft searchlight c1915 |
|
Training
At the beginning of the war the Royal Engineers had two main training
establishments; the School of Military Engineering, Chatham and
RE Training Depot, Aldershot, but the rapid expansion of the Army
(from 7 to 70 Divisions) and the demands that that imposed on the
need for training soon overwhelmed these establishments so the School
of Military Engineering was expanded and two satellite establishments
were set up to provide the extra capacity required to deliver training.
- Newark, Lincolnshire - opened Spring 1915. By August 1915 the establishment was training 3,000 men.
- Deganwy, North Wales - opened September 1915.
Both of these establishments were closed at the end of the war,
and the School of Military Engineering, Chatham resumed sole responsibility
for training.
|
Other Corps activities |
Transportation
- 1914 - The Royal Engineers Railway Transport Establishment managed
the mobilization of the British Expedition Force (BEF) in 1914.
- The Engineer and Railway Staff Corps rendered services to assist
in the movement of stores, troops and the management of the railways.
- 1916 - The Royal Engineers Inland Water Transport Section established
a Stores and Personnel Depot at Richborough, Kent. It was later
expanded to include the cross-Channel barge service.
- 1917 - The cross-Channel ferry was brought into operation
between Richborough and Calais with a supplementary service from
Southampton to Dieppe.
|
Inland Water Section Port at Richborough
c 1917. By 1918 it was a large well-equipped seaport, of 2,000 acres,
complete with all services and capable of handling 30,000 tons per
week. 242 barges (10 had a 1,000 ton capacity) were operated out
of the port on the cross-Channel barge service.
(Photo: thanetonline.com) |
Survey
- 1911 - The Geographic Section began work on
the preparation of maps of north-east France and Belgium which
were packed and made ready for issue on mobilization.
- 1913 - An extensive trigonometrical suvey of
Plymouth defences fixed positions of guns, datum points, depression
range finders and searchlights.
- 1914 - The Ordnance Survey was placed wholly
at the disposal of the War Office and with the help of the Royal
Geographic Society were able to assist the Royal Engineers to
met the demands for mapping placed upon them.
|
Postal |
- 1914 - Home Postal Depot was established in
the General Post Office (GPO) Mount Pleasant Building, London
to process army mail and to train members of the Postal Section.
By the end of the war it was staffed by 2,540 personnel. Mail
was sent by boat to the Base Army Post Office (BAPO) in the theatre
of war. The BAPO then organised the distribution of the mail to
units through the Field Post Offices (FPO).
- 1915 - An Army Parcel Sorting Office was built
in Regents Park, London. It was believed to be the largest wooden
building in the world covering an area of five acres.
- 1917 - The workload for processing army mails
became so great that part of the work was diverted to other GPO
sorting offices around the country.
|
|
|
Engineer-in-Chief BEF - At the beginning of the war the British
Expeditionary Force (BEF) only had an Engineer advisor, the Brigadier-General
Royal Engineers attached to the General Headquarters (GHQ) as it
was expected that he would not have "much to do in this war!".
However, it soon became apparent that he would have "much
to do" and consequently in January 1915 his position was
elevated to that of Chief Engineer, BEF. By July his function had
been further enhanced and he was given the title of Engineer-in-Chief
(E-in-C). |
|
In September 1915 he was authorised to correspond directly with
the field armies and corps on matters connected with the design
and pattern of engineer stores and general questions affecting Royal
Engineers equipment and issues.
The officers appointed as Engineer-in-Chief BEF were:
- 1915-16 - Brigadier-General (later Lieutenant
General Sir) George Fowke - he was promoted to the Adjutant-General
BEF
- 1916-17 - Major General (later Sir) Spring R Rice - In 1901
he invented the octagonal blockhouse used during the Anglo-Boer
war (1899-1902).
- 1917-18 - Major General (later Sir) Gerard M Heath.
In April 1916 it was laid down that the Engineer-in-Chief BEF should
report to the Chief of General Staff (CGS) in respect of operations
and defence, and the Quartermaster General (QMG) for works matters.
|
Lieutenant General Sir George Fowke,
first Engineer-in-Chief BEF promoted to Adjutant-General BEF in
1916 |
| With the establishment of the Engineer-in-Chief BEF
there came the creation of Chief Engineers for each Army and Corps,
who acted as technical advisors to their respective formation commanders.
|
1914 - The Corps and the war of movement
|
|
1914 - Tactical overview - The German Schieffen
plan aimed at striking a knockout blow on France by sweeping behind
French defences, via Belgium, and down through northern France to
capture Paris, began on the 2 August 1914.
The British Expeditionary Force (BEF) landed in France on 14 August.
Its engineer units included:
|
Major BEF Battles
Mons - 23 -26 Aug
Le Cateau - 26 Aug
Marne - 6-12 Sep
Aisne - 12 Sep
1st Ypres - 14 Oct - 22 Nov |
|
- Bridging Train (1st, 2nd Bridging Trains).
- Field (5th, 11th, 17th, 23rd, 26th, 56th, 57th, 59th Field Companies,
1st Field Squadron, 4th Field Troop).
- Fortress (30th, 42nd Fortress Companies).
- Railway (RTE, 8th, 10th Railway Companies).
- Printing (1st Printing Company) - This was a Survey unit.
- Postal (BAPO, Advance BAPO, 1st, 2nd Stationary Post Office).
- Signals (1st, 2nd, 3rd, 5th, Signals Company, 1st, 2nd, 3rd,
4th, 5th Signals Troops, A-F Airline Sections, F-P Cable Sections,
Q Wireless Section) .
- Works (29th Works Company).
The BEF first saw action against the Germans at Mons, Belgium on
23 August, where they were protecting the northern flank of the
French Army. The Allies (French and British) temporarily checked
the German's advance, but overwhelming numbers forced them into
retreat.
The British and French armies retreated south towards Paris, stopping
to hold a line on the river Marne. During the subsequent battle
of Marne, they collectively pushed the Germans back beyond the rivers
of Aisne, Oise and Meuse. After that battle the BEF were withdrawn
from the line and moved north, to secure a line between the river
Yser and the Flanders town of Ypres, where they fought the last
battle of 1914, the 1st battle of Ypres.
|
1914 - Divisional field engineering activities
| Divisional Engineers
The engineers of the Division were commanded by a Lieutenant
Colonel (the Commander Royal Engineers (CRE)). His Headquarters
usually consisted of 3 x officers, 10 x other ranks, 8 x horses,
2 x carts and a bicycle. He commanded two to three Field companies
and one Signals company. The Field Companies provided engineering
assistance in terms of construction of roads, defences, bridges,
the provision of water supplies, as well as the demolition of
obstacles and bridges. The Special (gas) or Tunnelling companies
after their formation in 1915 were also deployed in the Divisional
areas as circumstances required.
Works and other Royal Engineer specialist units (e.g. Inland
Water Transport, Postal, Railway, Searchlights, Survey etc.)
were usually commanded and deployed as Corps and/or Army troops.
|
Mons (23-26 August) - In the retreat from Mons
the engineer field units were engaged in demolishing railway and
road bridges. On 23 August 1914, Captain Theodore Wright and Lance
Corporal Charles Jarvis (both of 57th Field Company) won Victoria
Crosses for their actions demolishing bridges on the Mons-Condé
canal.
The Mons-Condé canal 24 August 1914 Taken the day after Corporal Jarvis' VC action and shows the German bridge built under fire from the Northumberland Fusiliers
(Photo: IWM Q70073) |
|
During the retreat from Mons the rear area units were evacuated
to the north west of France (St. Nazaire, Nantes and Le Mans).
Le Cateau (26 August) - At Le Cateau 59th Field
Company had its first experience of infantry fighting.
Marne (6-12 september) - After the breakthrough
and the subsequent advance to river Aisne the field engineers were
engaged in repairing and constructing bridges over the rivers as
the troops advanced.
1st Ypres (14 October - 22 November) - In the
lead up to the 1st battle of Ypres engineer field units were billeted
close behind the support line, they spent their days collecting
materials and their nights carrying them forward to construct entanglements
and other defences. On 11 November 5 Field Company won 7 DCMs in
an action at Polygon Wood - see 5th
Field Company at Polygon Wood
|
First World War - Sapper VCs
23 Aug 1914 - LCpl CA Jarvis (57 Fd Coy)
23 Aug 1914 - Capt T Wright (57 Fd Coy)
14 Aug 1914 - Capt WH Johnston (59 Fd Coy)
19 Dec 1914 - Lt P Neame (15 Fd Coy)
12 Mar 1915 - 2Lt CG Martin (56 Fd Coy)
7 Aug 1915 - Cpl CRG Bassett (NZ Div Sigs Coy)
25 Sep 1915 - 2Lt FH Johnson (73 Fd Coy)
13 Oct 1915 - Cpl JL Dawson (187 Fd Coy)
22 Jun 1916 - Spr W Hackett (254 Tunnelling Coy)
31 Jul 1917 - Brig-Gen C Coffin (25 Inf Bde)
22 Mar 1918 - 2Lt CL Knox (150 Fd Coy)
24 Aug 1918 - Sgt S Forsyth (NZ Engineers)
8 Oct 1918 - Capt CN Mitchell (1 Tunnelling Coy, 4th Canadian
Engineers)
4 Nov 1918 - Spr A Achibald (218 Fd Coy)
4 Nov 1918 - Maj GdeCE Findlay (409 Fd Coy)
4 Nov 1918 - Maj AHS Waters (218 Fd Coy)
6 Nov 1918 - Maj BM Cloutman (59 Fd Coy)
|
|
As autumn passed, the battle of Ypres died down and the Royal
Engineers were employed without respite on improving the trenches,
repairing roads, improving billets, and manufacturing all kinds
of trench stores, makeshift bombs, grenades, periscopes and mortars.
Nearly every field company had a bomb factory.
From September onwards more field units arrived in theatre: 2nd, 3rd Field
Squadrons, 2nd, 7th, 9th, 12th, 15th, 38th, 54th, 55th Field Companies.
During November 1914 elements of the Royal Monmouthshire Royal
Engineers (1st, 4th Siege Companies, 3rd Railway Company) and Royal
Anglesey Royal Engineers (1st, 2nd Siege Companies, 2nd Railway
Company) began to arrive in theatre (both were Special Reserve units).
In December the first of the Territorial engineer field companies
arrived in theatre: 1st Lowland, 1st East Anglian, 1st Cheshire,
1st (St Helens) West Lancashire, 1st and 2nd Home Counties, 1st
London, 2nd Highland Field Companies.
|
|
|
1914 - Other Corps activities
- Royal Engineers Railway Transport Establishment
(RTE)
- At the outset of war they organised and coordinated the
deployment of the BEF to France.
- During the Retreat from Mons they organised evacuation of
the rear areas to St. Nazaire, Nantes and Le Mans, and coordinated
the movement of British troops and stores by rail with the
French railway authorities.
- They organised the transportation, by rail, of Indian Corps
from Orleans to the neighbourhoods of Lillers, Merville and
Berguette (26 October-27 November) and the movement of rear
units from St. Nazaire, Nantes and Le Mans, back to northern
France.
- Works
- In August 1914 they established bases in Boulogne, Amiens,
Le Havre and Rouen and set up Lines of Communication.
- During the retreat they established bases in the north west
of France at St. Nazaire, Nantes and Le Mans which remained
open until January 1915.
- In September they re-established bases at Boulogne, Le Havre
and Rouen, with an advance base at Abbeville.
- In December, Dieppe became a British military station.
- Signals
- Established communications for BEF with telegraph connections
back to England.
- Survey
- They issued maps to troops on embarkation.
- The accuracy of maps became important during the Retreat
from Mons and thereafter surveys of northern France were made
to improve them.
- 1st Ranging Section was formed in November to assist the
artillery to locate an enemy target, by fixing the position
of an aeroplane signalling from a position vertically above
the enemy target.
- Postal
- Established Base Army Post Office at Le Havre, the advance
Base Army Post Office at Amiens and the two Stationary Post
Offices at Boulogne and Rouen.
- Mails were exchanged between Le Havre and Southampton.
- After the evacuation to north west France the Base Army
Post Office opened in Nantes and the Advance Base Army Post
Office at Le Mans.
|
A supplies being loaded at a railhead - the
Royal Engineers Railway Transport Establishment (RTE) was responsible
for coordinating with the French railway authorities the movement
of British troops and supplies.
(Photo: Realistic Travels Publishers)
Royal Engineers Signals' telegraph office
at a GCHQ base.
(Photo: Realistic Travels Publishers) |
1915 - The deadlock begins
1915 - Tactical overview - At the end of 1914
the Allied front began to settle on a relatively static line, that
ran from Neuport in the north to Nancy in the south. |
| In March the British began an offensive on the German front
lines, known as the battle of Neuve Chapelle, using the tactic of
heavy artillery bombardment followed by an infantry assault, it
had limited success.
On 22 April 1915 the Germans used poison gas for the first time,
and the British launched their second attack (2nd battle of Ypres)
in the Ypres area.
|
Major BEF battles
Neuve Chapelle -10-15 Mar
2nd Ypres - 22 Apr-25 May
Festubert - 16-27 May
Loos - 25 Sep-13 Oct |
|
| The summer passed away with minor attacks, and ended
with a main British offensive at Loos, but again little was gained. |
1915 - Divisional field engineering activities |
Trench tramway (1915) constructed by the Royal
Engineers divisional field engineers.
(Photo:IWM Q7908) |
Over the winter of 1914/15 constant shelling, and
heavy traffic, caused so much damage to the roads in the area of
the front, that they became almost impassable. This disrupted the
supply route between the refilling points and front lines.
The divisional engineer field units were tasked with resolving
the matter. Early in 1915 they devised a wooden 2ft gauge tramway,
to carry stores and ammunition between the refilling points and
the front line. The rails were made of 3in x 2in wood planks and
the sleepers of 1in planking. The wheels for the trucks came from
the mining area round Béthune, or from the factories of Armentières.
By May 1915, the tramways were used to remove stretcher cases, and
the spoil from tunnels. |
Neuve Chapelle (10-15 March) - In the build-up
to the battle of Neuve Chapelle, the tasks of the divisional engineer
field units included:
- Digging trenches and building breastworks for use as assembly
places for attacking brigades.
- Construction of additional communication trenches.
- Building splinter-proof shelters for brigade headquarters
and bomb depots.
- Laying wooden tramlines.
- Formation of advance depots for engineer stores.
|
|
- Construction of ladders for assaulting troops to use to
exit their trenches.
- Provision of light foot-bridges.
- Reconnaissance of ground.
- Cutting embrasures for machine-guns in front-line trenches.
- Issue of tools, sandbags etc to the infantry.
- Duckboards (or Trench mats) - were manufactured by Royal Engineers
and came into general use during 1915.
|
Examples of shelters and duckboards
built by the Royal Engineer field companies - 1917
(Photo: IWM) | |
Examples of trench ladders built
by the Royal Engineer field companies -1917
(Photo: IWM) |
|
Loos (25 September- 13 October) - Second Lieutenant
Frederick Johnston (73rd Field Company) was awarded a Victoria Cross
for his actions in leading a series of charges on a German redoubt
at Loos on 25 September 1915.
|
1915 - Other Corps activities |
- Tunnelling
- In April 1915 tunnelling and mining to attack the enemy
positions by tunnelling underneath them and then destroying
them with mines was began. The German held Hill 60, an artificial
mound adjoining the Ypres-Comines railway, about 2½
miles south of Ypres, became their first objective.
- Tunnelling was begun by a mining section formed from Welsh
miners of the 1st and 3rd Battalions Monmouthshire Regiment
attached to the 1st Northumberland Field Company, Royal Engineers
(TF).
- Gas
- In response to the German gas attack of April 1915, the
British deployed gas for the first time during the battle
of Loos on 25 September 1915. The gas was dispensed by the
'Special Companies' (186th, 187th, 188th, 189th) raised especially
for this type of warfare.
- On 13 October 1915, Corporal James Dawson (187th Special
Company) was awarded a Victoria Cross for preventing men from
being 'gassed' by faulty gas cylinders.
|
Sergeant Martin Fox of a Special Company,
Royal Engineers handling gas cylinders in the forward line. |
- Searchlights
- Searchlight units were deployed to Abbeville, Etaples and
Abancourt to provide lighting for air defence.
- In August 1915 experiments were conducted to illuminate
no-mans land with oxyacetylene lamps.
- Works
- Early in 1915 Etaples became a reinforcement camp and hospital
base.
- In March, 6 x Territorial RE, Fortress companies were in
theatre.
- In May, the port of Calais was taken into use.
- Other centres opened at Abancourt (supply depot), Le Tréport,
Fécamp, Etretat and Pont de L'Aube (hospitals).
- Shipping berths were constructed at Rouen, Boulogne and
Dunkirk.
- Aerodromes were built for the Royal Flying Corps (RFC).
|
- Signals
- In December 1915 the Royal Engineers Army Pigeon Service
was formed on its transfer from the Intelligence Section.
- Railway
- By the summer of 1915 11 x British Railway Construction
Companies were in service in France.
- Railway construction led to the doubling of the Hazebrouch-Poperinghe
line; building of new line from Candas to Acheax, sidings
at Abbeville, Calais and Blarges - in all 105 miles of track
was laid.
- Inland Water Transport
- Barges were used to carry bulky traffic of no great urgency,
travelling along the rivers and canals.
- Barges were fitted out with water pumping and water filtering
installations.
- Barges were fitted out to carry the wounded.
- Postal
- In January a second Base Army Post Office was opened at
Boulogne and a packet service was established between Boulogne
and Folkestone, Kent. This had the effect of providing a 12
hrs service from London to the the BEF Headquarters, and 24-48
hrs service to the majority of the front line.
- In June a third Base Army Post Office was opened at Calais.
- The in-theatre cross-post system was revised and improved.
- Survey
- During the build-up to the battle of Neuve Chapelle aerial
photography was, for the first time, used to make topographic
studies of the battle area.
- Sound Ranging (locating enemy artillery by sound) was introduced
in October 1915.
- Water
- In May 1915 a Water Supply Committee was established
(members were Royal Engineers and Royal Army Medical Corps officers).
They laid down scales for the supply of water to men and animals.
- Boring for water began.
|
Royal Engineers Signals horse drawn pigeon
loft (c1915)
(Photo: Royal Signals Museum)
Hospital barges in tow. The Royal Engineers
Inland Water Transport were responsible for the operation of the
barges and tugs used to tow them
(Photo: Unknown)
Water Cart (c1915) The supply of water was
a Royal Engineer responsibility.
(Photo: Realistic Travels Publishers)
|
1916 - The Somme and the deadlock continues |
| 1916 - Tactical overview - On 21 February 1916
the Germans launched a ferocious offensive on the French at Verdun,
which continued until November. The French appealed to the British
to counter-attack the Germans to relieve the pressure, because the
Germans were 'bleeding their [French] army white'.
|
Major BEF battle
Somme - 1 Jul-18 Nov
|
|
| Field Marshal Sir Douglas Haig (1861-1928), the British
Commander in Chief, however, was not prepared to launch any attack
on the Germans until at least July 1916, and then only after reinforcements
had arrived from Britain. He also wanted to ensure that there were
sufficient ammunition stocks and stores accumulated, and that appropriate
preparations had been made. The offensive was finally launched on
1 July and became known as the battle of the Somme, it ended on 18
November 1916. |
| 1916 - Divisional field engineering activities
|
|
Somme (1 July to 18 November) - The preparation
for the battle of the Somme for the field engineers was much the
same as in previous battles.
It was in the rear areas that the work of the engineers was different
and varied. Army Troops and rear engineers unit were heavily involved
in:
- Improving the rail and road links to the front.
- Ensuring that there
were sufficient supplies of water for the troops.
- Constructing accommodation for the concentration of the troops,
in this, the invention of the Nissen hut, by Major Peter Nissen,
Royal Engineers helped, although most accommodation was a wooden
framed hut covered by tarpaulins erected by the Royal Engineers.
|
Major Peter Nissen the designer of the 'Nissen
Hut' standing in front of one of his huts. The huts first came into
service in 1916 and were used to house troops in the build up to
the battle of the Somme |
RE Companies who
served on the Somme (July-November 1916) |
Division |
Field Company |
Guards |
55th, 75th, 76th |
1 |
23rd, 26th, 1/1st Lowland |
2 |
5th, 226th, 1/1st East Anglian |
3 |
56th, 1/1st Cheshire, 1/1st East Riding |
4 |
9th, 1/1st Durham, 1/1st Renfrew |
5 |
59th, 1/2nd Durham, 1/2nd Home Counties |
6 |
12th, 1/1st London, 2/2nd West Riding |
7 |
54th, 95th, 1/3rd Durham |
8 |
2nd, 95th, 1/3rd Durham |
9 |
63rd, 64th, 90th |
11 |
67th, 68th, 86th |
12 |
69th, 70th, 87th |
15 |
73rd, 74th, 91st |
16 |
155th, 156th, 157th |
17 |
77th, 78th, 93rd |
18 |
79th, 80th, 92nd |
19 |
81st, 82nd, 94th |
20 |
83rd, 84th, 96th |
21 |
97th, 98th, 126th |
23 |
101st, 102nd, 128th |
24 |
103rd, 104th, 129th |
25 |
105th, 106th, 130th |
|
Division |
Field Company |
29 |
1/3rd Kent, 1/2nd London, 1/1st West Riding |
30 |
200th, 201st, 202nd |
31 |
210th, 211th, 223rd |
32 |
206th, 218th, 219th |
33 |
11th, 212th, 222nd |
34 |
207th, 208th, 209th |
35 |
203rd, 204th, 205th |
36 |
121st, 122nd, 150th |
37 |
152nd, 153rd, 154th |
38 |
123rd, 124th, 151st |
39 |
225th, 227th, 234th |
41 |
228th, 233rd, 237th |
46 |
1/1st, 1/2nd, 2/1st North Midland |
47 |
1/3rd, 2/3rd, 1/4th London |
48 |
1/1st, 1/2nd, 2/1st South Midland |
49 |
57th, 1/2nd West Riding, 2/1st West Riding |
50 |
7th, 1/1st, 2/2nd Northumbrian |
51 |
1/1st, 1/2nd, 2/2nd Highland |
55 |
1/1st, 2/1st, 2/2nd West Lancashire |
56 |
1/1st Edinburgh, 2/1st, 2/2nd London |
63 (RN) |
1st, 2nd, 3rd Field Companies RN Division |
|
|
Army Troop Companies |
133rd, 134th, 135th, 145th, 148th, 149th, 214th, 216th, 221st, 232nd, 236th, 238th, 280th, 281st, 282nd
1/1st Hants (later 559th), 1/1st Wilts (later 265th),
1/3rd Cornwall (later 573rd), 1/1st Sussex (later 577th),
1/1st Devon (later 567th)
1st Siege Company Royal Monmouthshire Royal Engineers
4th Siege Company Royal Monmouthshire Royal Engineers
2nd Siege Company Royal Anglesea Royal Engineers |
|
Tunnelling Companies |
174th, 178th, 179th, 181st, 183rd, 252nd
|
| Other Royal Engineer units also present
in the forward areas but not listed above include: Postal,
Searchlights, Signals, Special (Gas), Survey and Tunnelling. |
Source: History of the Corps
of Royal Engineers Vol V (p. 273-4) |
|
| During the battle the field engineers were engaged in assisting
the infantry to negotiate obstacles, improving the lines of communications
immediately behind the front line to allow reserves to move forward
and ensuring that water was available to the frontline troops. |
1916 - Other Corps activities |
- Gas
- The Livens Projector was used during the battle of the Somme
to launch gas cylinders on the German lines. It was devised
by Captain FH Livens, Royal Engineers, and consisted of a
steel tube capable of firing a 30lbs phosgene bomb.
- In February 1916 a box respirator was issued to the Special
Companies.
- Works
- 1st Base Park Company was established at Attaques and Calais.
- 24th Base Park Company was established at Abancourt and
Rouen.
- 32nd Base Park Company was established at Le Havre.
- Camouflage
- The first Camouflage unit was set up on 22 March 1916 in
Amiens under the title 'Special Works Park RE'.
- In June another factory opened at Aire, France.
- They built and painted covers to hide guns, created camouflage
netting, built and painted observation posts to look like
trees, parts of trenches etc.
- The whole unit was disbanded in 1918.
- Quarry
- 2 Quarry companies were raised and deployed in France to
quarry hardcore for road repair and construction.
- Tunnelling
- The tunnellers were heavily committed tunnelling under German
lines and laying mines.
- Tunnelling companies also built underground bunkers to shelter
the troops an example was the 'Vampire' shelter constructed
by 171 Tunnelling Company RE
- On 22 June 1916 Sapper William Hackett of 254 Tunnelling
Company was awarded a posthumous Victoria Cross.
|
The Livens Projector was simply a metal pipe
about a metre or so long that was buried in the soil at a 45-degree
angle. Each projector was loaded with a drum containing about 14
kilograms (30lbs) of gas, and the bank of projectors was fired by
an electrical charge, sending the drums tumbling through air for
a range of over a 1.5km (about a mile).
The work of a camouflage artist Captain AR
Harker, Royal Engineers
|
Sapper William Hackett VC
(254 Tunnelling Company, Royal Engineers)
22 June 1916
Whilst in a tunnel at Givenchy, an explosion of an enemy mine
caused the gallery to collapse trapping Sapper Hackett and four
others. After working for 20 hours a hole was made through the
fallen earth, and three of the party made good their escape.
But Hackett refused to leave the fourth, who was seriously wounded,
saying "I am a tunneller and must look after the others
first". There was a further earth fall, and although
the rescue party worked desperately for four days, all attempts
to reach the two men failed. They could only leave Hackett and
the wounded man to their fate entombed in the earth.
William Hackett was awarded a posthumous Victoria Cross "well
knowing the nature of sliding earth, and the chances against
him, deliberately gave his life for his comrade". |
- Survey
- At the beginning of the year the topographical sections
became Field Survey Companies and schools were established
to teach 'Sound Ranging' and 'Flash Spotting' techniques.
- Development of artillery surveys continued, and the idea
of 'Flash Spotting' was further developed. The continual and
accurate observation of the front was carried out by the Artillery
Survey Section.
- Inland Water Transport
- In January 1916 a cross-Channel barge ferry service opened
between Richborough, Kent and Calais.
- By September 1916 the Inland Water Transport consisted of
58 tugs and 590 barges with a carrying capacity of 76,000
tons.
|
- Postal
- As a security measure (in June 1916) Field Post Office date
stamps that were used to cancel the mail were exchanged between
Field Post Offices to ensure that if any British mail was
captured by the Germans it could not be used to identify units
and formations (as was possible with captured German mail).
This security measure continued to the end of the war.
- Searchlights
- Searchlight units were used in an air defence role in the
rear of the forward battle areas during the battle of the
Somme.
- Signals
- The Fullerphone, invented by Captain (later Major General)
AC Fuller, Royal Engineers came into service. It was designed
to overcome 'eavesdropping' by the enemy. The Fullerphone
remained in service until the 1950's.
- Water
- By 1 July 1916 the engineers had, in the Fourth Army area,
established 100 water power pumps and laid almost 120 miles
of water mains. 126,000 gallons of water storage had be established
in the forward areas.
|
Field Post Office - September 1916
Near Deanancourt.
(Photo: IWM Q4108)
Fullerphone being used at a Listening post.
The Fullerphone first saw service in 1916.
(Photo: Royal Signals Museum)
|
1917 - Stalemate |
| 1917 - Tactical overview - January 1917 brought
little hope for the Allies as the British were still recovering
from the battle of the Somme and French from their ordeal at Verdun.
In March the German's made a tactical withdrawal to better consolidate
their defences. On the 6 April the French began their Nivelle offensive
on the Aisne, which ended in failure and in its wake mutinies broke
out amongst French units in May 1917. |
Major BEF battles
Arras - 9 Apr-4 May
Messines - 7-14 Jun
3rd Ypres (Passchendaele)- 31 Jul-10 Nov
Cambrai - 20 Nov -7 Dec |
|
Royal Engineer Tunnellers at Messines Ridge
June 1917
(Photo: Realistic Travels Publishers) |
On the 9 April the British and Canadians launch what has become
known as the battle of Arras during which they captured Vimy Ridge.
On 25 June the advance parties of the American Expeditionary Force
(AEF) arrived in France.
A third attack was launched at the end of July with the objective
of capturing the Passchendaele Ridge.
Tanks were used for the first time in the last British attack of
the year at Cambrai, but the momentum of the attack was soon lost
through a lack of reserves, thus ended another disappointing year
for the Allies.
|
| 1917 - Divisional field engineering activities During the German withdrawal in March, the field engineers were
engaged constructing bridges to assist the British forces to move
forward to occupy the vacant trenches, which the engineers then
reinforced. |
| Arras (9 April - 4 May) - In the preparation for
the battle of Arras, the main engineering problem (as it was for all
offensives), was that of having sufficient material for the construction
and repair of roads. The winter of 1916/17 had been very harsh and
caused the roads to suffer badly under the heavy pounding of the army's
mechanical transport. The need to accumulate ammunition for the planned
barrage at the beginning of the battle demanded that the roads should
be made ready to carry that traffic. The solution was to reorganise
the responsibility for roads, this resulted in the removal of much
of the responsibility from the shoulders of the Divisional field engineers
and to give it to the Army Troops engineers. |
Royal Engineers building a pontoon bridge across the Somme at Peronne, 22 March 1917
(Photo: IWM Q5833) |
Light railway wagons powered by a petrol-engined
Simplex locomotive, Elverdinghe February 1917
(Photo: IWM Q1696) |
The tramways were upgraded to light railways and their management given
over to a Director of Light Railways.
During the battle of Arras the field engineers were engaged in constructing strong points, bridging old British trenches, laying mule tracks, removing booby-traps, sign-boarding captured German trenches, and bombing and clearing German trenches.
|
Messines (7 - 14 June) - The Royal Engineer
Tunnellers were heavily engaged in the preparations for the battle
of Messines, which was begun by the explosion of 19 gigantic mines
laid by them. The explosions were designed to destroy the German's
front-line defences on a wide sector, and to demoralize their front-line
garrisons.
3rd Ypres (31 July - 10 November) - During the
3rd battle of Ypres (Passchendaele) the field engineers were engaged
in; improving the lines of communication, duck-boarding tracks,
bridging streams, constructing mule tracks, building advanced field
dressing-stations, building divisional unit battle headquarters
and building cover for field guns, screening roads in exposed places,
clearing blocked streams, removing obstacles from the path of tanks,
destroying bogged down tanks, hauling guns from the mire, and laying
tape to guide infantry units forward. The task of extending water
pipelines became impractical so the engineers had to construct water
storage tanks by the road side at which water could be collected
in petrol cans and carried forward. |
177 Tunnelling Company's tunnelling plan February 1917 |
Cambrai (20 November - 7 December) - The battle
of Cambrai was the first battle at which tanks were deployed in
earnest, although they had been deployed during the 3rd battle of
Ypres, they had only been so in an experimental capacity and contrary
to the advice of the Tank Corps Commander, the engineer Brigadier
General (later General Sir) Hugh Elles.
Tanks moving forward with infantry in close
support - 1917
(Photo: IWM)
In this first major tank battle Elles advanced in the leading
tank and led the newly formed Tank Corps to a great victory that
once and for all settled the controversy upon the value of tanks
and establishing them as a new arm in war. However, it was unfortunate
that the British had insufficient reserves to exploit the gains
made by the tanks.
| Tanks and the Royal Engineers

Elles |
Royal Engineer officers were heavily involved in the
development of the tank during the First World War (1914-18).
Colonel (later Major General Sir) Ernest Swinton was Secretary
of the War Committee that conceived the idea of tracked
armoured vehicles and it was he who christened the vehicle
- the 'tank'. The name was intended to be deceptive for
security reasons. It was the engineer Colonel (later General
Sir) Hugh Elles (1880-1945), who was selected to command
the 'Heavy Section', Machine Gun Corps, which became the
Tank Corps in May 1917. |
 Swinton |
|
|
After the victory at Cambrai the British line went into a state
fluidity and the defence of it was made more difficult due to a lack
of manpower. In December it was laid down that the defences should
be divided into three zones:
- Forward Zone - consisting of the firing line, support line and
communication trenches; the maintenance of the fabric of these
trenches became the responsibility of the divisional field engineers.
- Battle Zone - was an area sufficiently in rear of the Forward
Zone to allow artillery fire to be brought to bear on the enemy
if he broke through the former, and it came under the supervision
of corps engineers (army troop companies, tunnelling companies
assisted by labour companies and entrenching battalions).
- Rear Zone - was an area about 4-8 miles behind the Battle Zone
and also came under the supervision of corps engineers (army troop
companies, tunnelling companies assisted by labour companies and
entrenching battalions).
|
|
1917 - Other Corps activities
- Tunnellers
- Messines mine (see above).
- Underground shelters.
- Searchlights
- An Inspector of Searchlights was appointed.
- The Sections were organised and expanded to provide anti-aircraft
lighting to protect bases, ports and railway installations.
- Railway Transport Establishment
- On 28 June 1917 an overland service opened from Cherbourg
through Modane and Italy to Taranto on the Adriatic to serve
the Italian, the Macedonian and Middle East theatres of war.
- Signals
- In May members of the Women's Army Auxiliary Corps (WAAC)
were employed as Telegraph clerks in the rear area Telegraph
Offices.
- Signalling lamps used during the battle of Arras.
- Forestry
- 5 x Forestry companies were raised and deployed in France.
- Postal
- In May members of the Women's Army Auxiliary Corps (WAAC)
were employed as Postal clerks in the rear area Base Army
Post Offices and stationary Post Offices.
|
A Forestry company sawmill set up on the Amiens-Albert road November 1916 (Three quarters of the total
engineer stores consisted of timber or timber articles) (Photo: IWM Q4610)
Postal QMAAC with Colonel (later Sir) David
Lidbury, Deputy Director Army Postal Service BEF 1918. |
1918 - A setback and the final break through |
|
1918 - Tactical overview - The Germans spent the
winter of 1917/18 moving their troops from their Eastern Front to
the Western Front , where they prepared for a major offensive. It
began on 21 March under the operational name of 'Michael' but is
more usually known as their 'Spring Offensive'. They used the tactics
of storm troops which took the Allies by surprise and they managed
to break through the Allies' lines only to be halted before Amiens
where the Allies were able to impose a crushing defeat on the then
spent German army.
|
Major BEF battles
Spring Offensive - 21 Mar-early Jun
2nd Aisne - 27 May-2 Jun
Le Hamel - 4 Jul
2nd Marne -15 Jul-3 Aug
Havrincourt -12 Sep
|
|
| The defeat of the Germans at Amiens led to a succession
of defeats and by 2 September the Germans were in full retreat back
to the shelter of their Hindenburg Line, and there they held but pressure
was maintained by the Allies, and eventually the German line finally
broke. The Allies flooded through the gaps and rapidly advanced towards
Germany. In the first week of November 1918 the Germans sued for peace
of which terms were final agreed on 11 November 1918. |
| 1918 - Divisional field engineering activities
In the new year of 1918 there was some indication that the Germans
were preparing to launch an offensive so the engineers attended
to the defences of their respective Zones of responsibility. The
defensive measures included: the preparation of all bridges for
demolition, and their numbering both on the ground and on maps;
storing of the charges in chambers close at hand and the telling
off of firing parties, felling trees across roads, (the mining of
road junctions and causeways, was omitted because it was considered
more important that the tunnelling companies spend time making deep
dugouts).
|
|
Spring Offensive (21 March - June) - After the German
offensive began on 21 March the engineer units demolished the bridges
in the Forward Zone much of them under the cover of thick fog. Some
of the bridges were also demolished in the Battle and Rear Zones.
All units in the Forward and Battle zones got caught up in the fighting.
At Oxelaere, on 22 March 1918, Second Lieutenant Cecil Knox (150
Field Company) was entrusted with the demolition of 12 bridges to
hamper the German advance. In the case of one of the steel girder
bridges the fuse failed. Knox under heavy fire managed to detonate
the explosives and was awarded a Victoria Cross for his devotion
to duty.
|
An 84ft span Mark 1 Inglis bridge at La Motte April 1918 The Inglis bridge bore its inventor's name, Charles Inglis, a fellow of King's College Cambridge. |
|
On the 25 March a composite force of technical engineer units
(144th, 213th, 216th and 217th Army Troop Companies, 243rd Tunnelling
Company, 253rd Electrical and Mechanical Company, No 4 Workshops
Company, 5th Survey Battalion, two companies of 6th Regiment US
Engineers and a detachment Fifth Army Signals) was gathered together
to provide a defence for Amiens, the force was known as 'Carey's
Force'. It and other composite forces held the line and helped to
stabilise the situation in the Amiens area.
The German advance spent itself at the gates of Amiens and by May
and their fortunes were suddenly reserved.
|
The Allies advance (The last hundred days) (8
August - 11 November) - In the advance through the Hindenburg Line
and on towards Germany the divisional and Army Troop engineers were
deeply involved in assisting the armies to move forward, their work
included road and rail repair, reconstructing bridges across rivers
and canals.
In October while the Field squadrons were awaiting to accompany
their cavalry divisions forward they were engaged in the establishment
of water points, filling in road craters, making diversions and
searching for mines and traps.
During the advance east the BEF found that the Sambre-Oise Canal
formed a considerable obstacle. During the two days of 4-6 November
1918 four Victoria Crosses were awarded to engineers (Corporal Archibald,
Major Cloutman, Major Findlay and Major Waters) for laying bridges
across the canal. |
|
1918 - Other Corps activities
- Gas - the Special Companies continued to administer
gas attacks throughout the year.
- Water
- In August water had to be provided for an estimated 600,000
men and 300,000 animals. Transport lorries and GS (General
Service) wagons were fitted with water storage tanks and accompanied
the armies in their advance.
- An estimated 20 million gallons of water were transported
by road during the advance.
- Survey
- Produced and distributed maps containing water supply information.
|
A water pump erected by the Royal Engineers - 1917 (Photo: IWM) |
- Searchlights
- Continued to provide anti-aircraft lighting to
protect bases, ports and railway installations, particularly as
the nightly bombing intensified.
- After the Armistice the Anti-Aircraft searchlight sections
were used to illuminate work during the reconstruction of
demolished bridges and railways.
|
- Signals
- By 1918 the telephone was the main means of communication on the Western Front.
- Works
- During the first quarter of the year Royal Engineer stores
passed out of the Royal Engineer Store Yards at a rate of
140,000 tons per month.
|
Royal Engineers signallers using heligraph signalling in Feuchy, south of the Scarpe river - 1917 (Photo: IWM) |
- Postal
- Forward Field Post Offices were over run during the German
Spring Offensive.
- In June the Base Army Post Office at Calais was destroyed
by enemy bombing.
|
Italian Front - 1917-18
Tactical overview - On 24 October 1917, after a heavy shell and gas bombardment a combined Austro-German force attacked Italian troops in the upper valley of the Isonzo. The Italian forces broke and retreated 40 miles west, across the River Tagliamento to the River Piave. The Italian Government immediately requested Allied help.
|
An Anglo-French force, consisting of the British XIV Corps (23rd
and 41st Divisions),was despatched to Italy and began to arrive
on 11 November 1917. On the 13th, General Sir Herbert Plumer arrived
and assumed command of the British forces in Italy. Further Divisions
(5th, 7th, and 48th) joined the force, as did XI Corps headquarters.
The XI Corps headquarters, 5th and 41st Divisions returned to France
in February 1918.
In June 1918 the Austrians attacked along the Asiago plateau, but
were repulsed. Late in October, British forces attacked along the
Piave and succeeded in pushing the enemy back to the Vittorio Veneto
area, pressure was maintained until an Armistice was called by the
defeated Austrians early in November 1918. By then, units of the
British Army had also advanced into the Trentino area and were the
first such troops to enter the home soil of a European enemy during
the war. |
|
|
The engineers to accompany this force were:
- 59th, 491st (Home Counties) and 527th (Durham) Field Companies (5 Division)
- 474th, 475th, 477th Field Companies (48 Division)
- 54th, 95th and 528th (Durham) Field Companies (7 Division)
- 101st, 102nd, 128th Field Companies (23 Division)
- 228th, 233rd and 237th Field Companies (41 Division)
- 158th, 285th, 290th and 8th (monmouth) Army Troops Companies (LofC)
- 246 Base Park Company, dets 32 Base Park Depot, 5th Pontoon Park, 13th Reinforcement Company (LofC)
- 6th Field Survey Company (LofC)
- 34th AA Searchlight Section
- Signals and Postal units
|
|
Divisional field engineering activities
During the June 1918 Austrian offensive the field companies were
caught up in the fighting and the 474th and 477th Field Companies
were used to hold sectors of the British line. In August, during
a British attack, searchlights were used to produce artificial moonlight
across the battle field.
As part of the British offensive across the Piave river the field
engineers (54th, 95th, 528th (Durham), 128th Field Companies (and
later 101st) were required to construct a pontoon bridge from the
mainland to the Island of Papadopoli in the Piave river. Work began
on 24 October 1918 and was completed three days later. The engineers
were also employed with all movements connected with the crossings
by ferry and footbridges.
During the pursuit after the crossing of the Piave the 474th and
475th Field Companies made the routes up onto the Asiago plateau
passable for wheeled vehicles. At Sacile the 285th Army Troop Comany
constructed an Inglis girder bridge.
|
Other Corps activity
- Survey
- British Surveys on the Italian front began in November 1917.
- Works
- Arquata Scrivia was selected as the Base area for the Expeditionary
Force and a RE Stores Depot was established there.
- The port of Genoa was used for stores coming by sea, but
very few engineer stores came that way.
|
Post box in the 5th Pontoon Park compound
Italy 1918
(Photo: Proud) |
- Transportation
- Railway operating and road and railway construction was
arranged through the Italian Army Transportation Directorate.
- A small detachment of Royal Engineers were responsible for
maintaining the British-built rolling stock used as hospital
trains.
- Postal
- Divisional FPOs accommpanied their respective Dvisions.
- Initially there were delays in the mails arising from congestion
on the railways, so it was arranged that mails passed through
France on an express service to Modane and that a special
Travelling Post Office (TPO) operated between Modane and Padua,
where the British GHQ was located.
|
Middle East and the Balkans 1914-1919
Background - In 1914 Egypt was under Turkish (Ottoman
Empire) suzerainty, but had in fact been governed by Britain since
1882 (see Egyptian
Expedition 1882). Egypt was strategically important to Britain
and its Empire because it occupied the land bridge between Asia
and Africa and was traversed by the Suez Canal, which formed a vital
link in the Empire's sea route between Britain and her colonies
and dominions in the East (e.g. India, Hong Kong, Australia and
New Zealand). Its importance was further enhanced in 1908 when oil
was discovered in Mesopotamia (now Iraq) and the Persian Gulf.
|
Turkey (Ottoman Empire) declared its support for the Central Powers
(Germany, Austria-Hungary and Bulgaria) on 29 October 1914. Turkey's
assistance in the bombardment of Russia ports on the Black Sea forced
the Allies (Britain, France and Russia) to declare war on Turkey
on 5 November 1914.
All these reasons led to the decision that Egypt be established as a base for British troops operating in the Middle East and from which the Egyptian Expeditionary Force (1916-1918) grew and following expeditions were supplied:
- 1915-16 - Gallipoli Expedition - Dardanelles
- 1915-18 - Salonika Expedition - The Balkans
- 1915-17 - Senussi Campaign - Western Egypt
- 1916-19 - Palestine Campaign
|
|
Military Base, Egypt 1914-1919 |
1914 - Establishing the Military Base - Egypt
In August 1914 the engineers in Egypt consisted of:
- A small Works staff, under Colonel HBH Wright (Chief Engineer).
He was appointed Engineer-in-Chief, Egypt and Palestine in 1916.
- 2nd Field
Company
They were soon joined by 1st and 2nd (East Lancashire)
Field Companies of the East Lancashire Division (TF). The Royal Engineers provided accommodation for troops arriving in theatre with
assistance from the Egyptian Public Works Department. Camps were
built at Ismailia, Suez, Port Said and other locations along the
Canal.
During the winter of 1914-15 it became obvious that the eastern frontier of
Egypt and the Suez Canal zone, which adjoined territory of the Ottoman
Empire, required protection. 42 Division and the Indian Expeditionary
Force (10 and 11 Divisions) were charged with its defence. Divisions
from Australia and New Zealand (ANZAC) later joined them.
The engineers of these divisions were tasked with the defence works of these
areas, which consisted of a series of fortified bridgeheads covering
floating bridges. At each beachhead detached trenches revetted with
sandbags and covered by wire were constructed. A few electrically
fired land mines were built into the inner defences of the beachhead
at Ismailia. A small airfield was prepared at Moascar and searchlights
installed along the Suez Canal.
Still under development
|
|
Gallipoli Expedition - 1915-16
Tactical overview - The campaign took place between 25 April
1915 and 9 January 1916. The offensive's ultimate aim was to push
through the Dardanelles straits and capture Constantinople, the
Turkish capital. If a breakthrough had been achieved, the Turks,
who were allied with Austria and Germany (the Central Powers), would
have been unable to prevent Britain and France from joining the
Russians in the war against Austria-Hungary and Turkey.
After a failed bombardment of the Turkish forts at the Dardanelles
by the British and French navies it was decided that the capture
of the Gallipoli peninsula should be done by land forces. The forces
chosen were: the British 29th Division (commanded by the engineer
Lieutenant General Sir Aylmer Hunter-Weston), and divisions from
Australia and New Zealand (ANZAC). The attack began on the 25 April
1915 established two beachheads at Cape Helles and Gaba Tepe (ANZAC).
Another major landing took place at Sulva Bay on 6 August 1915.
However, attempts to sweep across the peninsula ended in failure.
By the end of August the Allies had lost over 40,000 men. General
Ian Hamilton (1853-1947), Commander-in-Chief of the expedition asked
for another 95,000 men, but although his request was supported by
Winston Churchill (1874-1965), Kitchener was unwilling to send more
troops to the area.
|
|
On 14 October 1915, Hamilton was replaced by General Sir Charles Munro (1860-1929).
After touring all three fronts Munro recommended withdrawal. Lord
Kitchener, who arrived two weeks later, agreed that the 105,000
men already on the peninsula should be evacuated. The evacuation
operation began at Sulva Bay on 7th December. The last of the men
left Helles beaches on 9 January 1916.
About 480,000 Allied troops took part in the Gallipoli campaign.
The British suffered 205,000 casualties (43,000 killed). There were
more than 33,600 ANZAC losses (over one-third killed) and 47,000
French casualties (5,000 killed). Turkish casualties are estimated
at 250,000 (65,000 killed).
|
Lord Kitchener at ANZAC, Gallipoli 13 November
1915 returning from Russel's Top and Bully Beef Sap, General Birdwood
behind him
(Photo: IWM Q13547)
|
|
Command of the engineers Brigadier-General AW Roper was appointed 'Technical Adviser to the Commander-in-Chief' but was not present when Hamilton was planning the operation from the island of Lemnos. Indeed no British engineer officer in a technical capacity was present at any of the planning stages. |
|
Mudros Bay, Lemnos - Expedition's Advance Base
Mudros Bay was chosen as the Advance Base for the force, but as
a base it was very under developed. There were no adequate piers
and wharves, no roads, no light railways, few buildings and a scant
water supply. The engineers who were tasked (13th Base Park Company
and 1/3rd (Lancashire) Workshop Company) with the establishment
of the base were also hampered by the shortage of stores, skilled
labour and an inappropriate command structure. The original companies
detailed with the development were later joined by four Army Troop
companies and the 117th Railway Company.
|
By the end of December 1915 the following had been achieved:
- 7 x piers had been constructed and a further seven were under construction.
- 1 x General hospital (1,040 beds), 2 x stationary hospitals (624 beds each), 1 x infectious hospital had been constructed.
- A railway connecting the piers, camps and hospital had been
constructed.
- A water condensing plant (33,000 gallons a day) was operational.
In May 1915 the General Headquarters (GHQ) was established on the Island of Imbros where it remained until the evacuation (January 1916). The 1/3rd (Lancashire) Workshop Company setup a small advance workshop on the island. |
|
Cape Helles Front - April 1915- January 1916
The Landings - April 1915
The landing by a force 35,000 men (29th Division) at Cape Helles
on the Gallipoli peninsula 's southern tip took place at five locations
('S', 'V','W', 'X', and 'Y', Beaches).
|
The engineers
of 29th Division involved were:
- S beach - 1/2nd London Field Company
- V beach - 1/1st West Riding Field Company
- W beach - 2/2nd Lowland Field Company
Their tasks were to tackle the very formidable Turkish wire entanglements,
to construct a causeway for guns.
On the first night of the landings the engineers, whilst under
constant fire and with only the light of flares also assembled several
barrel piers, dug wells, and constructed a light trestle bridge.
|
|
|
Formation of VIII corps - July 1915
In July 1915 all troops ashore at Helles were formed into VIII
Corps under command of the engineer Major General Sir Aylmer Hunter-Weston.
The Corps' engineers were:
- 29th Division - 1/2nd London, 1/1st West Riding, 2/2nd Lowland Field Companies.
- Royal Naval Division - 1st, 2nd, 3rd Field Companies
- 42nd Division - 1st (later 427th), 2nd (later 428th) East Lancashire Field Companies.
- 52nd (Lowland) Division - 2/1st, 1/2nd Lowland Field Companies.
- Corps Troops - 13th Base Park Company, 254th Tunnelling Company and a Postal unit.
On the beaches the engineers continued to construct and repair
piers damaged by stormy seas. They also dug shelters to protect
those on the beaches. They laid causeways and a decauville (narrow
gauge railway) across the beaches. A Steam Tractor was used to haul
in timber from sunken barges.
The 1/1st West Riding Field Company supervised the construction
of an artillery road to the front, which ran four miles inland.
At the front the engineers constructed redoubts within 80 yds of
the Turkish trenches, they also manufactured bombs, built shell
proof shelters and laid much of the wire in no-man's land. In June
1915 the 254th Tunnelling Company was tasked with the execution
of the 29th Division mining offensive.
|
|
|
During the offensives against the Turks the engineers who followed
close behind the assault troops were engaged in converting capture
trenches for British use. They also constructed bridges over trenches
to carry guns much in the same way as their counterparts did on
the Western Front.
The evacuation - 7-9 January 1916
In preparation for the final evacuation the engineers constructed
defences to cover the beaches, this was done with help from the
infantry. The engineers also blocked all the communication trenches
that there were not to be used during the evacuation and carefully
marked those that were to be used.
The piers on 'W' and 'V' beaches were used to evacuate troops into
K lighters, which ferried them out to the waiting battleships. The
engineers were detailed to stayed to the end to repair damage to
any of the piers. |
Preparing the evacuation, W Beach, Cape Helles,
7 January 1916. Note the piers which were built and maintained by
the Royal Engineers.
(Photo: IMW Q 13692) |
ANZAC (Ari Burnu) Front - April-December 1915
15km north from Cape Helles, on the Aegean coast of the Gallipoli
peninsula, the Australian and New Zealand Corps (ANZAC) comprising
17,000 men were landed at Ari Burnu ('Z Beach'), 1.5km north of
Gaba Tepe (where the landing was actually intended). French troops
were also part of this force. The ANZAC were accompanied by their
own engineers; their tasks and experiences were the same as of those
of the Royal Engineers.
|
| Corporal (later Colonel) CRG Bassett, New Zealand Divisional Signals
Company, was awarded a Victoria Cross for laying, under a continuous
fire, a telephone line from the old postion to the new one on Chunuk
Bair ridge, Gallipoli on 7 August 1915. |
Corporal CRG Bassett VC |
Suvla Bay Front - August-December 1915
The Landings - August 1915
The landings of the IX Corps (10th, 11th and 53rd Divisions) at Suvla Bay ('A', 'B' and 'C' beaches) begun on the evening of 6 August and ended on 9 August. The field engineers involved were:
|
- 10th Division - 65th, 66th, 85th Field Companies (landed 7 August 1915).
- 11th Division - 67th, 68th and 86th Field Companies (landed 6 August 1915).
- 53rd (Welsh) Division - 1st Welsh, 2/1st and 2/2nd Cheshire Field Companies (landed 9-11 August 1915).
So fierce was their reception that they were engaged in fighting
in an infantry role, as well as having to carry out they usual tasks
of constructing shelters, sangars (stone breastworks) and trenches,
improving paths and the water supply. The Official Corps history
records:
|
Royal Engineer Signals Despatch Riders preparing
for duty on the Suvla beach - 1915
(Photo: Royal Signals Museum) |
"No account of the landings at Suvla gives a true picture if it omits reference to the prevalence among these young troops of dysentery. To be thrown into battle for the first time on an unknown desert shore was a fierce enough ordeal for the vanguard of Kitchener's New Army. Yet these men were called upon to march, often in the clutches of a weakening disease. These were officers and men of whom our Corps may well be proud." As on the other landing beaches the engineers constructed piers - eleven in all. |
|
ANZAC and Suvla evacuation - 7-19 December 1915
A description of the engineers work in the preparation for the evacuation was reported in The Times: "…the work of the sappers was to impede their [the Turks] advance in case they did find out [about our intensions to evacuate] and go for us. The [engineer] officers and men went out at night between our parapets and those of the enemy, which were only a few yards apart, putting up wire and laying down land mines - jumpy work, especially as the last few days the waning moon made it a close business whether we could finish the job or not…"
Thanks to the work of the engineers, who constructed the defences,
roads and bridges as well as maintained the piers a total of 83,048
officers and men, 186 guns, nearly 2,000 vehicles and 4.695 horses
and mules were successfully evacuated from the ANZAC and Suvla beaches.
|
|
Other Corps activities
- Survey
- Although plans were to take a field survey section with
the expedition in the end none were taken.
- A map for the attack was hastily constructed by the Geographicl Section, but it contain inaccuracies which caused many difficulties.
- After the landings a map was found on a captured Turkish
officer which was sent to the Survey of Egypt where it was
reproduced for distribution.
- A Map and Printing Section was sent to Mudros late in 1915.
|
- Postal
- A Base Army Post Office was established at Mudros, mail
to and from home was despatched via Alexandria, Egypt.
- Field Post Offices accompanied the formations on the Gallipoli
Peninsula and mails were exchanged daily between them and
the Base Army Post Office at Mudros.
|
|
Senussi Campaign 1915-17
Tactical overview - In the autumn 1915 the Senussi,
a Muslim sect that lived on the Libyan/Egyptian borders, declared
a jihad (a holy war) against the Allies and pursued a military campaign
in the Egyptian Western Desert. A small force called the Western
Frontier Force, was assembled at Matruh, Egypt to counter-attack
the Senussi. The campaign which was fought on the western borders
of Egypt was very fluid and continued until April 1917.
|
The engineers involved were:
- 1/1st and 1/2nd Kent Field Companies - They constructed roads,
defences, water supply and a pier at Sollum.
- 2/1st Cheshire Field Company (released November 1916) - They
took over a pontoon bridge at Bahr YUsuf and replaced it with
a barrel pier bridge. Before they left the theatre they bore water
holes to supply the railway.
- 1/1st Welsh Field Company (53rd Division) - They built a road
between El Alamein and Moghara complete with blockhouses. They
were replaced by 37th Army Troops Company (May 1916).
- 5th Royal Anglesey Militia (replaced 37th Army Troops Company)
- They worked on the Baharia railway set up a water suplly system
that supplied 180,000 gallons per week, built a 100 ft span pontoon
bridge over the Bahr Yusuf west of Samalut, and constructed blockhouses.
They left the theatre in April 1917.
The Royal Engineers contributed in no small measure to the removal
of the threat to Egypt's security from the west. Throughout these
operations they were confronted with the problems of inadequate
supplies and inexperienced troops all of which had to be administrated
over vast areas.
|
|
Salonika Campaign 1915-18
Still under development |
| |
|
Palestine Campaign - 1916-18
Still under development
|
| |
|
Mesopotamia Campaign - 1916-18
Still under development
|
| |
|
West and East African Campaigns - 1914-18
Still under development
|
| |
|
Author: SC Fenwick, FoREM
Sources:
- History of the Corps of Royal Engineers
Vol V, VI, VII (Institution of Royal Engineers, Chatham, 1952)
- A Short History. The Royal Engineers. Compiled by Maj DP Aston RE (Institution of Royal Engineers, Chatham, 1993)
- Follow the Sapper. Napier G (Institution of Royal Engineers, Chatham, 2005)
- The Oxford Illustrated History of the British Army Ed: Chandler D, Beckett I (OUP, Oxford, 1994)
- A Short History of the British Army Sheppard EW (Constable, London, 1950)
|
Royal
Engineers Museum main site
|
|